Article 2. Electrical Code
4-201 National electrical code adopted.
The NFPA 70 National Electrical Code, 2020 Edition (hereinafter the “standard code “), as published by the National Fire Protection Association, One Batterymarch Park, Quincy, Massachusetts, 02269, as amended herein, including Annex C (Conduit and Tubing Fill Tables) and Annex H (Administration and Enforcement) and chapters 34 through 42 of the 2021 International Residential Code (IRC) is hereby adopted and incorporated herein by reference, as if fully set out in this section, subject to such amendments thereto as are set forth hereinbelow. The standard code is hereby adopted as the electrical code for the City of Park City, Kansas.
(Ord. 1178-2023)
4-202 Certificates and licenses.
A holder of a residential wireman electrician certificate may perform the act of installing all electrical wiring within or on one- and two-family dwellings only and must be in the employ of a licensed electrical contractor. Apprentice electricians or helpers shall be permitted to perform the act of installing any electrical work when he or she is on the job site with and under the supervision of a master, journeyman or residential wireman electrician certified and both are in the employ of a licensed electrical contractor. Job site is defined as the property that an individual permit is issued for. A numeric ratio of apprentices or helpers to certified master, journeyman, or residential wireman electricians on any one job site shall not be greater than four apprentices and/or helpers for each certified electrician.
If an apprentice electrician or helper works without the required supervision, both the electrical contractor license holder and the apprentice electrician/helper shall be guilty of a violation of the terms of this section.
Upon presentation by the code official to the Electrical Board of charges against the holder of any certificate or license the Electrical Board shall fix a time and place for a meeting to consider such charges and shall notify the holder of such certificate or license to be present at such meeting.
Such notification shall be in writing and shall be presented to the holder at least five days in advance of the meeting. If upon full hearing of all evidence by the Electrical Board it shall be decided that such holder of a certificate or license has been guilty of any of the actions as hereinbefore set forth in this section, then the board shall have the power to place on probation for a specified time, temporarily suspend or permanently revoke the license or certificate of the holder thereof.
(Ord. 1178-2023)
4-203 Electrical permit fees
Table No. 80.19(D)(2) ELECTRICAL PERMIT FEES
The fee for each electrical permit shall be as set forth and shall accompany each application made for such permit.
EXCEPTION: Installations for new one-and two-family dwellings shall not be required to obtain an individual electrical permit or to pay an electrical permit fee, since the applicable Building Permit Fee which shall have been issued and paid are inclusive of the electrical installation.
| CIRCUITS | UNIT FEE | |
|---|---|---|
| 1 | 120 Volt Circuit | $2.00 |
| 2 | 277 Volt Circuit | $2.00 |
| HEATING APPLIANCES | UNIT FEE | |
| 3 | Heating Appliance less than 4500 watt | $3.00 |
| 4 | Range or Heat Device 4500 watt or over | $8.00 |
| 5 | Clothes Dryer | $8.00 |
| SPECIAL CIRUITS AND ADDITIONS | UNIT FEE | |
| 6 | Feeder | $9.00 |
| 7 | Hot tub/sauna or Jacuzzi | $14.00 |
| 8 | Special Power Circuit | $9.00 |
| 9 | Generator | $9.00 |
| SPECIAL CIRCUITS AND ADDITIONS | UNIT FEE | |
| 10 | Sign Per Circuit | $7.00 |
| 11 | Outlets Added to Existing Circuit | $0.75 |
| 12 | Smoke Detectors | $0.75 |
| FIXTURES | UNIT FEE | |
| 13 | Light Fixture or Lamp holding Device (also retrofits of fixtures) | $0.75 |
| MOTORS AND AIR COND | UNIT FEE | |
| 14 | 1 HP or less | $15.00 |
| 15 | Over I HP | $17.00 |
| 16 | Water Well Motor | $17.00 |
| SERVICE (NEW/CHANGE) | UNIT FEE | |
| 17A | 480 Volts or less (per meter – 100 Amps or less) | $22.00 |
| 17B | 480 Volts or less (Each additional Amp) | $0.06 |
| 18 | Over 480 Volts (Each Service Entrance) | $71.00 |
| 19 | Construction Service (480 volts or less) | $14.00 |
| 20 | Construction Service (over 480 volts) | $28.00 |
| MISCELLANEOUS | UNIT FEE | |
| 21 | Re-inspection of discontinued service (meter reset – one meter per permit) | $21.00 |
| 22 | Transformer | $11.00 |
| 23 | Miscellaneous | $14.00 |
| 24 | Permit Issuance Fee | $30.00 |
* Any person who performs any electrical installation work for which a permit and inspection are required, and who fails to report the same as ready for inspection when such work is completed for not longer than one business day, or fails to obtain a permit prior to performing the work, shall pay a Special Permit Fee of twice the amount of the scheduled fee charges shown above for said permit, which shall be no less than Twenty-Five Dollars ($25.00), in addition to payment of the Regular Permit Fee. In circumstances where re-inspections are made because of faulty construction or failure to make necessary repairs, a Re-inspection Fee of Thirty Dollars ($30.00) shall be paid.
(Ord. 1178-2023)
4-204 NEC 2020 Section [201.8(A) (5)] is amended as follows:
NEC 2020 210.8(A)(5) and 2021 IRC E3902.5. Exception. Receptacles installed in finished areas of the basement intended to be used as habitable rooms are not required to have GFCI protected receptacles.
(Ord. 1178-2023)
4-205 NEC 2020 Section [210.8(A) (1-11)] and IRC Chapter [E3902 (1-11)]:
NEC 2020 210.8(A) (1-11) and 2021 IRC E3902 (1-11). The requirements for all 250-volt outlets to be GFCI protected are deleted except for what is required in 2020 NEC Article 680 and 2021 IRC Chapter 42.
(Ord. 1178-2023)
4-206 NEC 2020 Section [210.12(A through D)] and 2021 IRC Chapter [E3902.17] are amended as follows:
Arc-Fault circuit interrupter protection shall only be required for the circuits in all sleeping areas, excluding smoke detector wiring.
(Ord. 1178-2023)
4-207 NEC 2020 Section [230.67] and 2021 IRC Chapter [E3601.8] are amended as follows:
Requiring the installation of Surge Protection is deleted.
(Ord. 1178-2023)
4-208 NEC 2020 Section [230.70(A)(1)] and 2021 IRC Chapter [E3601.6.2] are amended as follows:
The service disconnecting means shall be installed at a readily accessible location either outside of a building or structure or inside. Unfused service entrance conductors routed to the service disconnecting means shall not be extended more than 15 feet inside any structure.
(Ord. 1178-2023)
4-209 NEC 2020 Section [230.82(10) ,230.85] and 2021 IRC Chapter [E3601.5] are amended as follows:
Requiring the installation of Emergency Disconnects is deleted.
(Ord. 1178-2023)
4-210 Repealed.
(Ord. 1178-2023; Ord. 1241-2026)
4-211 NEC 2020 Section [210.8 (A) (5), Exception] and 2021 IRC Chapter [E3902.5 Exception 2] are amended to read as follows:
Exception. Sewage Ejector Pumps and Sump Pumps. In a dwelling, ground fault circuit interrupter protection shall not be required on a sewage ejector pump or sump pump that is cord and plug connected and installed on a dedicated circuit run to a single receptacle.
(Ord. 1178-2023)
4-212 NEC 2020 Section [210.70] and IRC Chapter [E3903.4] are amended by adding the following:
(5) Unfinished Basements. Each storage area and all future habitable rooms that are in the framed-in stage shall have a lighting outlet with a wall mounted switch for each area or room. Lighting outlets containing a switch shall be controlled by a wall switch.
(Ord. 1178-2023)
4-213 Copies on file; to be furnished.
Not less than three (3) copies of the standard code shall be filed with the City Clerk. Said copies shall be marked or stamped “Official Copy” with all sections or portions thereof intended to be omitted clearly marked to show any such omissions. Said copies shall have attached a copy of this ordinance and shall be open to inspection and available to the public at all reasonable business hours. Copies in numbers as needed shall also be furnished without charge by the department of code enforcement of the city to the courts and all administrative departments charged with enforcement of the standard code.
(Ord. 1178-2023)
4-214 Adoption of rules and regulations.
The building official shall have the authority to promulgate such rules and regulations as are necessary to carry out the purpose of the standard code and such rules and regulations shall be effective upon approval by the Governing Body.
(Ord. 1178-2023)